RPG Stage 2: Planning


Stage 1: Pre-Planning Stage 2: Planning Stage 3: Plan Submission

you@YOUR Machine:
  1. Start sswidl and invoke EIS Planning Tools in Remote Planning mode (with rp keyword);
    SSWIDL>eis_mk_plan,/rp
  2. Prepare the EIS plan.

  3. When finished, ensure "Test CPT" runs successfully. During the CPT testing process a file $HOME/eis_cpt_properties.txt is created. This stores the current CPT parameters (ie; the start, stop and upload times, the OP/OG and OBSTBL Upload Pass IDs, and the names of the CP, CO and Tohban). This file may be used as a convenient way of inputting these parameters into the command-line CPT routine (however, they may also be modified later).

  4. Exit IDL;
    SSWIDL>exit